Week Ten of Manor Waste Refurbishment

  |  Published: Mar 30th 2016
more services to contend with under the Manor Waste surface
more services to contend with under the Manor Waste surface

This week work will take place on the binder course, drainage channel, electrical duct and chambers and kerbing. There will also be more La Linia blockwork, Speedcheck/Tescina, blister paving and bollards. Work on the Budgens entrance should be finished this week.

To read about the survey completed prior to this work, click here

To see some videos of work in progress click here

To see what happened in week one, click here

To see what happened in week two, click here

To see what happened in week three, click here

To see what happened in week four, click here

To see what happened in week five, click here

To see what happened in week six, click here

To see what happened in week seven, click here

To see what happened in week eight, click here

To see what happened in week nine, click here

  • Tuesday 29 March: more services to contend with under the Manor Waste surface
  • Wednesday 30 March: much progress today with drainage course and services ducting
  • Thursday 31 March: as predicted, some paving was laid today
  • Friday 1 April: most of the last of the old surface was removed today

To see what happened in week eleven, click here

To see what happened in week twelve, click here

To see what happened in week thirteen, click here

To see what happened in week fourteen, click here

To see what happened in week fifteen, click here

To see what happened in week sixteen, click here

To see what happened in August, click here

Browse our Articles

Articles By Date
Search our Articles
Search
Back to top